Hampden Avenue

Natural Gas Project

Englewood, CO

November 2024 – Spring 2025

Overview

We replaced approximately 2,000 feet of natural gas line and replaced customer service lines along Hampden Avenue, between Lincoln and Clarkson streets, in Englewood, Colorado. This work allows us to continue to provide safe, reliable natural gas service and enhances system resiliency during extreme weather.

We coordinated with the City of Englewood’s Old Hampden Utility Improvements Project taking place along Hampden Avenue, between Broadway and Emerson Street.

Construction update

Friday, May 23, 2025

Crews have completed construction and restoration of the Hampden Avenue Natural Gas Project.

It was our pleasure to work in your community, and we thank you for your patience and cooperation while we completed this project.

Construction on the City of Englewood’s Old Hampden Utility Improvements Project taking place along Hampden Avenue, between Broadway and Emerson Street, is ongoing.

Schedule

Construction began in November 2024 and was completed in May 2025.

What you can do

If you have questions or comments, we want to hear from you.

Call us at 303-312-8841 or email [email protected] to learn more.

Safety

Public safety is at the foundation of all we do. The safety of the public around our natural gas system influences every decision we make.

If you ever suspect a natural gas leak, leave your home or business immediately. Once you are safely away, call 911, then Xcel Energy at 800-895-2999.

For more information on our commitment to safety, please visit our Public Safety page.

Document Library

Address
Please contact me about my comment(Required)
This field is for validation purposes and should be left unchanged.

Contact Us

Have a question or want to provide feedback?
Call 303-312-8841
Email [email protected]
Fill out the comment form above

Scroll to Top