I-76 to Leyden Street
Natural Gas Project

Project Area: Adams County, CO
Project Dates: 2020 – 2021

Project Complete

The I-76 to Leyden Street Natural Gas Project has been successfully installed and is now in service. We thank the community for their patience and cooperation while we constructed this critical natural gas project.

Xcel_Energy_I-76_to_Leyden_Street_Project_Map

Project Information

We have replaced approximately 1.6 miles of 10-inch natural gas in Adams County for the I-76 to Leyden Street Natural Gas Project.

This work is our commitment to system revitalization, allowing us to continue to provide you safe, reliable service. It also accommodates and supports growth and enhances resiliency during extreme cold weather.

For information on our commitment to safety, please visit our Public Safety page.

Construction began February 2021 and was completed in late 2021. We installed the west segment first followed by the east segment in late 2021.